Winchmore Hill, N21

A complete demolition of an existing property and full rebuild of a 4 story house including basement.

Project Outline

Client: Private
Architect: BB Partnership

We completely demolished the existing structure and in its place, our expert team meticulously built a luxurious four-story home. The new property boasts a newly added basement complete with a state-of-the-art cinema, a fully equipped gym, a plant room, a temperature-controlled wine cellar, and a generously sized bar area.

By incorporating ample glass elements into the design, we were able to flood the interior with natural light, elevating the overall living experience to a truly exceptional standard.

Exterior

Our team ensured the exterior work met the highest standards by diligently constructing a luxurious four-story home after demolishing the existing structure.

Client
Private Client

Year
2021

Welcoming you inside

Demolishing an old property and building a new luxury home.

Interior

The property underwent the highest level of specification during its renovation, resulting in the creation of a brand-new home from the foundation upwards.

Inside, it boasts a recently excavated basement, a fully-equipped gym, a plant room, and a wine cellar. Furthermore, the entire residence was impeccably finished, featuring a tailor-made staircase, unique windows, and bespoke interiors.

Client
Private Client
Year
2021

“I would have no hesitation placing Sullivan Brothers on the tender lists of most residential and commercial projects.”

Neil Gaskell, BB Partnership

Winchmore Hill, N21

Facts of the Project

Below is a summary of what went in to completing the project.

Consultation to finished project, the building times and budget.

  • This project was also completed during covid so the big task was trying to complete the project on time as all suppliers lead times dramatically increased.

    We managed to bulk buy materials and store them at our yard and brought them as and when required to site to ensure we maintained the programme and the project was completed on time for the client.

    Once again, we managed to think outside the box to ensure the clients needs were met.

Building Times - 65 weeks

Budget - £2.8 million